What a submittal is, how submittals fit into Oversite, the fields on a submittal, the statuses and dispositions they move through, who can do what, and links to every submittals task.

A submittal is a formal document a contractor sends to the reviewing authority for approval before fabrication or installation. Shop drawings, product data, samples, certifications, mix designs, warranties, test reports, and operations and maintenance manuals are all common submittals. Oversite tracks each submittal through a defined review process, records the reviewer's decision, and always shows whose turn it is to act.

How submittals fit into Oversite

Submittals live on each project. To open them, go to the Project Group that contains your project, click the Project name, then click Submittals in the project navigation. The Submittals page lists every submittal for that project in a table.

You can also open a company-wide Submittals list to see submittals across all of your projects. The company-wide and group views add a Project column so you can tell which project each submittal belongs to.

Every submittal has two sides. The contractor prepares the submittal, attaches documents, sends it for review, and creates a revision when the reviewer asks for changes. The reviewer, a CEI or Agency company, acknowledges the submittal, reviews the documents, records a decision, and attaches review documents. A reviewer can also create a submittal on a contractor's behalf.

What is on a submittal

Field

Description

Submittal #

A number Oversite assigns automatically, such as SUB-001. Revisions keep the same number with a revision label added, such as SUB-001 Rev 1.

Title

A short description of the submittal.

Submittal Type

The kind of document: Shop Drawing, Product Data, Sample, Certification, Mix Design, Warranty, Test Report, O&M Manual, or Other.

Priority

High, Medium, or Low. New submittals default to Medium.

Description

Details about the submittal, materials, or specifications.

Required Date

The date the submittal is needed.

Review Due Date

The date the review is expected to be completed.

Contractor

For submittals a reviewer creates on a contractor's behalf, the contractor the submittal belongs to.

Submittal Manager

The project manager responsible for the submittal.

Status

The current stage in the review process.

Disposition

The reviewer's decision once the review is complete.

Ball in Court

Whose turn it is to act next, the contractor or the reviewer.

Attachments

The documents attached to the submittal. Reviewers can also attach review documents.

Submittal statuses and who has the ball in court

The status shows where a submittal is in the review process. The Ball in Court value shows whose turn it is to act next.

Status

Meaning

Whose turn

Draft

Created but not yet sent for review.

Contractor

Submitted

Sent to the reviewer and waiting to be acknowledged.

Reviewer

Under Review

The reviewer has acknowledged the submittal and is reviewing it.

Reviewer

Approved

Approved as submitted.

Contractor

Approved as Noted

Approved with notes or minor conditions.

Contractor

Revise & Resubmit

Changes are required before approval.

Contractor

Rejected

Not approved.

Contractor

Closed

Finalized. No further review will take place.

No action needed

Submittal dispositions

A disposition is the reviewer's decision once the review is complete. The reviewer records one of four dispositions.

Disposition

Meaning

Approved

Approved as submitted, with no changes needed.

Approved as Noted

Approved with notes or minor conditions. A resubmission is usually not required.

Revise & Resubmit

Changes are required. Create a revision and submit it again.

Rejected

Not approved.

The detail page shows a five-step progress indicator, so you can follow a submittal from Create Submittal, to Submittal Sent, to Under Review, to Disposition, and finally to Closed.

Who can work with submittals

What you can do with submittals depends on your role and on whether your company is the contractor or the reviewing authority on the project.

Action

Admin

Project Manager

Supervisor

Inspector

Viewer

View submittals

Yes

Yes

Yes

Yes

Yes

View draft submittals

Yes

Yes

Yes

No

No

Create submittals

Yes

Yes

Yes

No

No

Edit draft submittals

Yes

Yes

Yes

No

No

Delete draft submittals

Yes

Yes

Yes

No

No

Take workflow actions

Yes

Yes

Yes

No

No

Export

Yes

Yes

Yes

Yes

Yes

Project Managers and Supervisors can delete only draft submittals their own company created. Administrators can delete any draft their own company created. Reordering draft submittals is available to Administrators, project managers, and supervisors, for drafts their own company created. Inspectors and Viewers cannot reorder.

Which workflow actions you see depends on your side of the review. Contractors see Submit for Review, Create Revision, and Close Submittal. Reviewers see Acknowledge Receipt, Begin Review, Set Disposition, and Close Submittal. Only reviewers can create a submittal on a contractor's behalf. Inspectors and Viewers can see submittals once they are submitted, but cannot see drafts, create or edit submittals, or take workflow actions.

Working with submittals

These articles walk through each submittals task:

  • Create a submittal covers creating manually, creating from a PDF, editing a draft, adding attachments, reordering drafts, and deleting a draft.

  • Move a submittal through review covers submitting, acknowledging, beginning a review, setting a disposition, creating a revision, and closing a submittal.

  • View, filter, and export submittals covers opening the list, the table columns, filtering by status, and exporting a submittal or the list.

Frequently asked questions

Does Oversite send an email when a submittal needs my attention?
Submittals do not currently send automatic email notifications. Watch the Ball in Court and Status columns to see which submittals are waiting on you, and let the other party know directly when you take an action.

How do I know whose turn it is?
The Ball in Court value shows whether the submittal is waiting on the contractor or the reviewer. In the list, it is highlighted when the submittal is waiting on your side.

Can I use submittals on my phone or tablet?
Yes. You can access submittals from any device with a web browser, and the layout adapts to smaller screens. You can upload photos and documents directly from your device.