Review a contractor's request, send a change order to the contractor and owner for signature, sign or decline it, and approve it.

After a change order is drafted, it moves through an approval process before its changes take effect on the project. The CEI routes the document, the contractor and owner sign, and the CEI approves it. This article covers each action on the change order's Review screen. To create a change order first, see Creating a Change Order.

Every change order shows a Ball in Court pill for who needs to act next: the CEI, the contractor, or the owner. When the ball is in your court, the pill is highlighted so you can spot the change orders that need your attention.

How to review a change order request (CEI)

When a contractor submits a request, it appears with a status of Requested and the ball in the CEI's court. Open the change order to reach the Review screen, then use the Workflow panel.

To accept the request and turn it into a working change order:

  1. Open the change order.

  2. In the Workflow panel, click Promote to Draft.

The request becomes a Draft you can edit and route for signature.

To decline the request:

  1. In the Workflow panel, click Reject Request.

  2. (Optional) Add a message for the contractor.

  3. Click Confirm Rejection.

A rejected request becomes Archived.

How to send a change order for signature (CEI)

When a draft is ready, route it for signature from the Workflow panel on the Review screen. Send it to the contractor first, then to the owner after the contractor signs.

To send to the contractor:

  1. Open the change order.

  2. Click Send to Contractor.

The status becomes Sent to Contractor, the ball moves to the contractor, and the contractor receives an email that it is their turn to sign.

After the contractor signs, the change order returns to your court. To send to the owner:

  1. Open the change order.

  2. Click Send to Owner.

The status becomes Sent to Owner, the ball moves to the owner, and the owner receives an email.

Note: Send to Contractor appears only when the project has a contractor assigned as a stakeholder, and Send to Owner only when the project has an owner assigned. If the project has no contractor or owner to route to, approve the change order directly.

How to sign or decline a change order (contractor or owner)

When a change order is in your court to sign, open it to reach the Review screen. The action panel shows Contractor Signature or Owner Signature and tells you the change order is awaiting your signature.

To sign:

  1. Click Sign as Contractor or Sign as Owner.

  2. Draw your signature in the box.

  3. Click Save Signature.

After you sign, the change order returns to the CEI's court.

To decline:

  1. Click Decline.

  2. Enter a reason. A reason is required.

  3. Click Confirm Decline.

A declined change order returns to the CEI's court with your reason shown on the approval trail. The CEI can address it and re-send it for signature.

Note: While it is not your turn, the change order is read-only and you see an Awaiting CEI Response panel instead of the signing actions.

How to approve a change order (CEI)

CEI and agency users approve, or complete, a change order from the Workflow panel.

  1. Open the change order.

  2. Click Approve.

When you approve a change order, its item and timeline changes are applied to the project, the project's adjusted end date is locked in, and the status becomes Completed. The CEI, contractor, and owner all receive a confirmation email.

You do not have to collect every signature before approving. When a project has no contractor or owner to route to, click Approve to complete the change order directly.

Troubleshooting

The Send to Contractor or Send to Owner button is missing

The project may not have a contractor or owner assigned as a stakeholder. You can approve the change order directly instead. Also check that the change order is in a status that can be sent.

A change order is read-only when I open it

It is not your turn. Check the Ball in Court pill to see who needs to act. Stakeholders can only act when the change order is in their court.

My signature will not save

Make sure you have drawn in the signature box before clicking Save Signature. An empty box does not save.

I cannot approve a change order

Approving is limited to CEI and agency manager roles: Administrator, Super Admin, and Project Manager.

Frequently asked questions

Can I approve a change order without collecting every signature?

Yes. Click Approve to complete a change order directly. This is useful when a project has no contractor or owner to route to.

Why can't I send a change order for signature?

The Send to Contractor button appears only when the project has a contractor assigned as a stakeholder, and Send to Owner only when it has an owner assigned. If neither exists, approve the change order directly.

Does declining a change order notify anyone?

No email is sent, but the CEI sees your decline reason on the change order's approval trail and can address it.

Who gets notified when I take an action?

Oversite emails the relevant party when a contractor requests a change order, when the CEI sends it to the contractor, when the CEI sends it to the owner, and when the CEI approves it. Signing, declining, promoting, and rejecting do not send emails.