Run the Weather Days report

Open the Weather Days report for a project or group, read the Total Weather Days and Imbalance Count, filter by date range, and export to PDF or CSV.

The Weather Days report gives you a chronological log of the weather days you have recorded, with the inspector, the inspection reference, and the weather notes for each. It is available for a single project and for a whole group.

How to open the Weather Days report

  1. Navigate to the Project or the Group.

  2. Open the Reports area.

  3. From the report list, select Weather Days.

The report opens on the Report View page and loads the full project or group history by default.

What the Weather Days report shows

At the top, a summary card shows:

Field

Description

Date Range

The window the report covers. It defaults to the project or group lifetime until you choose a start and end date.

Total Weather Days

The number of separate calendar dates recorded as weather days on approved or completed inspections.

Imbalance Count

The difference between the weather days recorded and the calendar days added to the project by approved change orders that extended the completion date.

Below the summary is a table with one row per weather day:

  • Date - the date of the inspection.

  • Inspector - the team member who created the inspection.

  • DWR Reference - a link to the daily inspection the weather day came from.

  • Weather Notes - the notes recorded on that inspection.

The group report adds a Project column, a subtotal row for each project, and a Grand Total Weather Days figure across the group.

What the Imbalance Count means

The Imbalance Count compares two numbers: the weather days you have recorded, and the calendar days that approved change orders have added to the project's completion date. A positive number means you have logged more weather days than the time extensions granted so far. This is often the figure a scheduler watches when deciding whether to request more time. For how time extensions are granted, see Creating a Change Order.

How to filter the report by date range

  1. On the Report View page, find the date pickers under Report Options.

  2. Choose a start date, then an end date.

  3. The report reloads to cover only the range you selected.

To return to the full history, reopen the report from the report list.

How to export the Weather Days report

  1. Open the Weather Days report.

  2. Under Download Options, choose PDF to download a formatted report for sharing or filing, or CSV to download the data for a spreadsheet.

Both exports include the weather day rows and the totals. The group export also includes the project column and the per-project subtotals.

Troubleshooting

A weather day I recorded is not in the report

Check that the inspection has been approved or completed. Draft and in-review inspections do not count toward the report. Confirm the Weather Day toggle was set to Yes on that inspection. Then check the report's Date Range and set it to cover the inspection date, or reopen the report to see the full history.

The report shows no weather days

No inspections in the selected range have been marked as a weather day on an approved or completed inspection. Widen the Date Range or reopen the report to view the full project or group history.

Frequently asked questions

Which inspections count toward the Weather Days report?

Only inspections that have been approved or completed count toward the totals. Draft inspections and inspections still in review are not included.

If I record two inspections on the same day and both are weather days, does that count as two?

No. Weather days are counted by calendar date, so the same date counts once, even across multiple inspections.

What does a positive Imbalance Count mean?

It means you have recorded more weather days than the number of calendar days approved change orders have added to the project's completion date. It is a quick way to see whether recorded weather delays have been matched by granted time extensions.

Can I run a weather report across all my projects at once?

Yes. Open the Weather Days report at the group level. It lists weather days for every project in the group, with a subtotal for each project and a grand total.